| Hard bait schedule |
Hard bait schedule: --- Design; including profile date projector, 3d design, CNC sample; --- 3weeks; --- Prototype sample approval; --- 1weeks; --- Tooling building; --- 6weeks; --- Final sample approval; --- 2weeks; --- Production; --- 6weeks;
12weeks to final sample approval for ODM project ; production leadtime is 6weeks;
1. Design;
|
 |
2. Prototype sample approval; |
 |
3. Tooling building;
|
 |
4. Final sample approval;
|
 |
5. Production;
|
| 3weeks |
|
1week |
|
6weeks |
|
2weeks |
|
6weeks |
|
|